Add Activity Percent Complete Attribute (#765)
Browse files Browse the repository at this point in the history
  • Loading branch information
joniles authored Oct 29, 2024
1 parent b586bbc commit a7a0a31
Show file tree
Hide file tree
Showing 6 changed files with 46 additions and 1 deletion.
1 change: 1 addition & 0 deletions mkdocs/docs/field-guide.md
Original file line number Diff line number Diff line change
Expand Up @@ -190,6 +190,7 @@ ACWP| | | | | | | |✓| | |✓| | | | | | | | | | | | | 
Active|✓|✓|✓|✓|✓|✓|✓| |✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓
Activity Codes|✓|✓|✓|✓|✓|✓|✓| |✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓|✓
Activity ID|✓| |✓| | | | | | | | |✓|✓| |✓|✓|✓| | |✓| |✓|✓| 
Activity Percent Complete|✓|✓| |✓|✓|✓| | |✓|✓|✓|✓|✓|✓|✓|✓|✓| | |✓| |✓|✓| 
Activity Status| | | | | | | | | | | | | | |✓|✓|✓| | | | | | | 
Activity Type|✓| |✓| | | | | | | | | |✓| |✓|✓|✓| | | | | | | 
Actual Cost| | | | | | | |✓|✓|✓|✓| | | |✓|✓|✓| | |✓| | | | 
Expand Down
1 change: 1 addition & 0 deletions mkdocs/docs/mpp-field-guide.md
Original file line number Diff line number Diff line change
Expand Up @@ -149,6 +149,7 @@ Field|MPP8|MPP9|MPP12|MPP14
% Work Complete|✓|✓|✓|✓
Active|✓|✓|✓|✓
Activity Codes|✓|✓|✓|✓
Activity Percent Complete|✓|✓|✓|✓
Actual Cost|✓|✓|✓|✓
Actual Duration|✓|✓|✓|✓
Actual Duration Units| |✓|✓|✓
Expand Down
1 change: 1 addition & 0 deletions src/changes/changes.xml
Original file line number Diff line number Diff line change
Expand Up @@ -7,6 +7,7 @@
<body>
<release date="unreleased" version="13.5.2">
<action dev="joniles" type="update">Added the `Task.getBaselineTask()` methods. For applications where a separate baseline schedule is present or a baseline has been manually added to the `ProjectFile` instance, these methods will allow you to access the underlying baseline task instance from the current task instance.</action>
<action dev="joniles" type="update">Added the Activity Percent Complete attribute to the `Task` class. The value of this attribute will be the Duration, Physical or Units percent complete value, based on the Percent Complete Type setting. This attribute is provided as a convenience to match the Activity Percent Complete type value shown in P6.</action>
</release>
<release date="2024-10-28" version="13.5.1">
<action dev="joniles" type="update">Fix CVE-2024-49771: Potential Path Traversal Vulnerability</action>
Expand Down
1 change: 1 addition & 0 deletions src/main/java/net/sf/mpxj/LocaleData.java
Original file line number Diff line number Diff line change
Expand Up @@ -1058,6 +1058,7 @@ public static final String[] getStringArray(Locale locale, String key)
TASK_COLUMNS_ARRAY[TaskField.SHOW_START_TEXT.getValue()] = "Show Start Text";
TASK_COLUMNS_ARRAY[TaskField.SHOW_FINISH_TEXT.getValue()] = "Show Finish Text";
TASK_COLUMNS_ARRAY[TaskField.SHOW_DURATION_TEXT.getValue()] = "Show Duration Text";
TASK_COLUMNS_ARRAY[TaskField.ACTIVITY_PERCENT_COMPLETE.getValue()] = "Activity Percent Complete";

RESOURCE_COLUMNS_ARRAY[ResourceField.ID.getValue()] = "ID";
RESOURCE_COLUMNS_ARRAY[ResourceField.NAME.getValue()] = "Name";
Expand Down
40 changes: 40 additions & 0 deletions src/main/java/net/sf/mpxj/Task.java
Original file line number Diff line number Diff line change
Expand Up @@ -5484,6 +5484,17 @@ public boolean getShowDurationText()
return (BooleanHelper.getBoolean((Boolean) get(TaskField.SHOW_DURATION_TEXT)));
}

/**
* This accessor method returns the percent complete value for this task
* as defined by the Percent Complete Type attribute.
*
* @return activity percent complete
*/
public Number getActivityPercentComplete()
{
return (Number) get(TaskField.ACTIVITY_PERCENT_COMPLETE);
}

/**
* Retrieve the effective calendar for this task. If the task does not have
* a specific calendar associated with it, fall back to using the default calendar
Expand Down Expand Up @@ -5879,6 +5890,33 @@ private List<Relation> calculateSuccessors()
return getParentFile().getRelations().getSuccessors(this);
}

private Number calculateActivityPercentComplete()
{
PercentCompleteType type = getPercentCompleteType();
if (type == null)
{
return getPercentageComplete();
}

switch(type)
{
case UNITS:
{
return getPercentageWorkComplete();
}

case PHYSICAL:
{
return getPhysicalPercentComplete();
}

default:
{
return getPercentageComplete();
}
}
}

/**
* Supply a default value for constraint type.
*
Expand Down Expand Up @@ -5982,6 +6020,7 @@ private Boolean defaultExpanded()
CALCULATED_FIELD_MAP.put(TaskField.EXTERNAL_PROJECT, Task::calculateExternalProject);
CALCULATED_FIELD_MAP.put(TaskField.PREDECESSORS, Task::calculatePredecessors);
CALCULATED_FIELD_MAP.put(TaskField.SUCCESSORS, Task::calculateSuccessors);
CALCULATED_FIELD_MAP.put(TaskField.ACTIVITY_PERCENT_COMPLETE, Task::calculateActivityPercentComplete);
CALCULATED_FIELD_MAP.put(TaskField.CONSTRAINT_TYPE, Task::defaultConstraintType);
CALCULATED_FIELD_MAP.put(TaskField.ACTIVE, Task::defaultActive);
CALCULATED_FIELD_MAP.put(TaskField.TYPE, Task::defaultType);
Expand Down Expand Up @@ -6010,5 +6049,6 @@ private Boolean defaultExpanded()
dependencies.calculatedField(TaskField.CRITICAL).dependsOn(TaskField.TOTAL_SLACK, TaskField.ACTUAL_FINISH);
dependencies.calculatedField(TaskField.COMPLETE_THROUGH).dependsOn(TaskField.DURATION, TaskField.ACTUAL_START, TaskField.PERCENT_COMPLETE);
dependencies.calculatedField(TaskField.EXTERNAL_PROJECT).dependsOn(TaskField.SUBPROJECT_FILE, TaskField.EXTERNAL_TASK);
dependencies.calculatedField(TaskField.ACTIVITY_PERCENT_COMPLETE).dependsOn(TaskField.PERCENT_COMPLETE_TYPE, TaskField.PERCENT_COMPLETE, TaskField.PERCENT_WORK_COMPLETE, TaskField.PHYSICAL_PERCENT_COMPLETE);
}
}
3 changes: 2 additions & 1 deletion src/main/java/net/sf/mpxj/TaskField.java
Original file line number Diff line number Diff line change
Expand Up @@ -1037,7 +1037,8 @@ public enum TaskField implements FieldType
REMAINING_WORK_NONLABOR(DataType.DURATION),
SHOW_START_TEXT(DataType.BOOLEAN),
SHOW_FINISH_TEXT(DataType.BOOLEAN),
SHOW_DURATION_TEXT(DataType.BOOLEAN);
SHOW_DURATION_TEXT(DataType.BOOLEAN),
ACTIVITY_PERCENT_COMPLETE(DataType.PERCENTAGE);

/**
* Constructor.
Expand Down